ValueAdmin $500/mo; subscription $2.60/kW-mo; back-up power $1.15/kW/day demand + energy at avoided cost plus greater of $0.027/kWh or 10% of avoided cost; maintenance power $0.65/kW/day + avoided cost plus greater of $0.015/kWh or 10%
Deadlinesongoing tariff; standby agreement min 1-year term
RequirementsPURPA Section 210 Qualifying Facility; subscribed standby capacity <50 MW per facility; maintenance power scheduled >=10 days ahead, max 8 periods/60 billing days per year
Caveatssystem-wide cap 500 MW subscribed standby capacity; exceeding subscribed capacity triggers firm-rate demand charges up to 12 months; verified revision effective 07/01/2024, a 2026 revision is listed in Cleco's index
Last verified2026-08-12