ValueUp to $2.5 million per CHP system: design/installation incentives capped at $350/kW (<250 kW) or $250/kW (>=250 kW), plus $0.07/kWh production incentive after commissioning
DeadlinesOngoing; program manual covers 2024-2026 cycle
RequirementsBGE C&I customer regardless of supplier; reciprocating engine or gas turbine; minimum 65% annual efficiency (HHV); sized not to exceed 100% of historical annual consumption or peak demand
CaveatsBGE program page returned 403 to automated fetch — figures from BGE program materials/manual (2024-2026) surfaced via bgesmartenergy.com; confirm current terms directly with BGE before relying; cycle ends 2026