ValueITC 30% (6% base + PW&A) plus 10-pt domestic content and 10-pt energy community adders; PTC alternative under 45Y
Deadlines2027-12-31 — OBBBA: solar/wind beginning construction on/after 7/5/2026 must be placed in service by 12/31/2027 to qualify (BOC-before-7/5/2026 window has passed); projects that began construction earlier keep 4-year completion runway
RequirementsPlaced in service by 12/31/2027 for new-start solar; PW&A for full rate; FEOC ownership and material-assistance rules (40% non-FEOC content threshold for 2026 construction starts, rising annually; Notice 2026-15 interim MACR safe harbors); Notice 2025-42 tightened beginning-of-construction to physical-work test (5% safe harbor only for <=1.5MW solar)
CaveatsNow a ~14-month race to energize for new solar; Notice 2026-15 (2/12/2026) gives interim material-assistance safe harbors (temporary-identification, cost-percentage, supplier-certification) pending proposed FEOC regs; no new beginning-of-construction guidance since Notice 2025-42 as of 10/30/2026; residential-style lease structures restricted
Last verified2026-10-30